Klingle Road Implementation Strategy
Overview
The week of May 5, 2003, Mayor Williams and the District
of Columbia Council agreed to providing funding for reopening Klingle
Road as a paved roadway. In the Fall 2003, DDOT began the process
of obtaining Federal Highway Administration (FHWA) and National Park
Service (NPS) approvals for this roadway project. Below is the
DDOT Klingle Road Implementation Strategy.
Action |
Number of
Months to Complete Estimated in
June 2003 |
Number of
Months to Complete Estimated in January 2004 |
Number of
Months to Complete Estimated in September 2004 |
Preconstruction and Safety
improvements; remove hazards |
2 months |
8 months |
9 months |
Storm Water Hydrology Analysis |
3 months |
8 months |
1 year, 3 months |
Environmental Impact Statement (EIS) |
8 months |
1 year |
1 year, 6 months |
Design |
9 months |
9 months |
9 months |
Construction |
1 year |
1 year |
1 year |
9/27/04
|